Job Cost Variance: Reading Estimate vs Actual Before the Job Ends

Most contractors learn a job lost money when it closes. By then the only thing left to do is write it down.
A job cost variance report gives you the same news earlier, while there is still work to run. This article shows how to read one, which lines need a call today, and how to turn what you see into a revised forecast. For background on the basics, see job costing for contractors.
What a variance report shows
A variance report puts three numbers side by side for each cost line on a job: what you estimated, what you have spent, and the difference. Over budget is an unfavorable variance. Under budget is favorable.
The report only means something once you know how far along the job is. Say a job has a $400,000 cost estimate and you have spent $200,000. If the job is 50 percent done, you are on budget. If it is 40 percent done, you are about $40,000 over where you should be. The dollars are the same. The answer is different.
So read every variance against percent complete, not against the full estimate. A line that shows "$85,000 spent of $120,000 budget" looks fine until you learn the work is 60 percent done. Then the budget for that point was $72,000.
Base percent complete on a documented, measurable milestone where you can, such as quantities installed. If you cannot, use the project manager's own estimate, and know that it can be biased. If you derive it from cost, a cost overrun makes the job look further along, and the variance hides itself.
Labor: hours versus rate
Split every labor variance into two parts.
- Hours variance: you used more or fewer hours than the estimate allowed. Multiply the extra hours by the estimated rate.
- Rate variance: each hour cost more or less than the estimate assumed. Multiply the actual hours by the difference in rate.
The two have different causes. Extra hours point to productivity, rework, poor sequencing or a crew that was short on the first day. A higher rate points to overtime, a more expensive crew mix, or an estimate that used the wrong burden. Burden is what payroll costs you on top of wages, such as payroll taxes, workers comp and benefits, and it belongs in the labor rate. See labor burden in construction for how to build it.
Materials: price, waste and scope never estimated
Material overruns come from three places.
- Price: the supplier charged more than the estimate assumed.
- Waste: more material was bought or lost than planned, through cuts, damage, theft or over-ordering.
- Scope never estimated: items that were not in the estimate at all. This is the one to watch, because it is often a change order you have not priced or billed.
Check the third one first. If the cost belongs to work the owner asked for, the fix is a change order, not a smaller variance. See job costing mistakes for how unbilled extras slip through.
Subcontractors and equipment
Subcontract lines are usually the easiest to read, because the commitment is a contract. Compare the contract value, approved changes, and billed to date. A sub line that is on budget today can still be a problem if the sub has pending change requests you have not logged.
Equipment is noisier. Rental invoices arrive late, so a small favorable or unfavorable swing may be timing. Look at the trend over a few months before reacting.
Company-owned equipment is not free to run. Charge it to jobs at an internal hourly or daily rate based on its true ownership and operating costs. Have the field team log machine hours on daily reports, then allocate that cost to the job so margins reflect reality.
Noise versus a call today
Not every variance needs action. A rough sort:
Probably noise
- A small variance on a small line.
- A swing that reverses when a late invoice posts.
- A favorable variance on a line that is not finished, which often means a cost has not arrived yet.
Needs a call today
- A variance that is growing month over month.
- An overrun on a large line, since even a modest overrun there can be real money.
- Any cost for work outside the estimate.
- A labor overrun on a job with a lot of work still to do, since the same pace repeats on the remaining hours.
There is no fixed dollar or percent trigger for a call. It takes judgment about the line, the trend, the cause and the work still left.
A worked example
These numbers are invented to show the math. They are not from a real job.
LNH Contractors Inc has a $500,000 contract with a $400,000 cost estimate, so the planned profit is $100,000, or 20 percent. The project manager reports the job is 60 percent complete. The budget at 60 percent is therefore 60 percent of each line.
Labor was estimated at 2,000 hours at a burdened rate of $70, or $140,000. At 60 percent that is 1,200 hours and $84,000. The crew has booked 1,300 hours at an actual rate of $72, or $93,600.
| Line | Full estimate | Budget at 60% | Actual to date | Variance |
|---|---|---|---|---|
| Labor | 140,000 | 84,000 | 93,600 | 9,600 over |
| Materials | 120,000 | 72,000 | 85,000 | 13,000 over |
| Subcontractors | 100,000 | 60,000 | 62,000 | 2,000 over |
| Equipment | 40,000 | 24,000 | 22,000 | 2,000 under |
| Total | 400,000 | 240,000 | 262,600 | 22,600 over |
The check: 9,600 + 13,000 + 2,000 - 2,000 = 22,600. And 262,600 - 240,000 = 22,600.
On subcontractors, the signed subcontracts total $102,000, including a $2,000 approved change. That is $62,000 billed to date and $40,000 remaining.
Now split the two big lines.
Labor, $9,600 over:
- Hours: 100 extra hours (1,300 less 1,200) at the estimated $70 is $7,000.
- Rate: 1,300 actual hours at $2 more per hour is $2,600.
- Together: $7,000 + $2,600 = $9,600.
Materials, $13,000 over. Say the purchasing records show:
- Price increases: $4,000.
- Waste: $3,000.
- Items never in the estimate: $6,000.
- Together: $4,000 + $3,000 + $6,000 = $13,000.
The job has spent 65.7 percent of its estimate ($262,600 of $400,000) while the work is 60 percent done. That gap is the early warning.
What gets a call today: the $6,000 of unestimated material (is any of it billable?), and the 100 extra labor hours (why, and does it continue?). The equipment variance is probably timing, meaning a rental invoice that has not arrived yet. The sub variance matches the $2,000 approved change. If the owner is paying for that change, it is covered. If you absorbed it, it is a real overrun.
Turning variance into a revised cost to complete
The variance tells you what happened. The forecast tells you what it means for profit. For the full method, see cost-to-complete forecasting.
Start with the simple version. Cost to date is $262,600. The original budget for the remaining 40 percent is $160,000. If nothing else goes wrong, the job finishes at $422,600, and profit falls from $100,000 to $77,400, or 15.5 percent.
That version assumes the problems stop today. Usually they do not. So adjust each line for what you know:
| Line | Remaining original budget | Adjustment | Revised cost to complete |
|---|---|---|---|
| Labor | 56,000 | 867 hours at $72 instead of 800 at $70 | 62,424 |
| Materials | 48,000 | add 4,667 for price and waste to continue | 52,667 |
| Subcontractors | 40,000 | balance of signed subcontracts | 40,000 |
| Equipment | 16,000 | add 2,000 for the rental invoice still to come | 18,000 |
| Total | 160,000 | 173,091 |
The labor math: hours to date ran 8.3 percent over (1,300 against 1,200). At that pace, the remaining 800 budget hours become about 867. Then 867 hours x $72 = $62,424.
The material math: price and waste ran $7,000 over on the $72,000 budget to date. The same ratio on the remaining $48,000 is about $4,667. The $6,000 of unestimated items is not repeated.
The equipment math: the $2,000 under budget is a bill that has not posted, not a saving. It still has to be paid, so it goes into the cost to complete. If you confirm the bill is not coming, take it back out and keep the saving.
Revised cost at completion: $262,600 + $173,091 = $435,691. Profit is $500,000 - $435,691 = $64,309, or 12.9 percent. That is $35,691 below the original $100,000.
If the $6,000 of unestimated material is approved as a change order, add it to revenue and the margin improves. If not, you know now, with 40 percent of the job left to act. You can reset crew size, reprice remaining purchases, and ask for the change order while the owner is still listening.
Run the report monthly against a current percent complete. A late report is a history lesson. A current one is a tool.
I help contractors keep job costing, WIP and cash reporting current as their fractional controller. Schedule your Contractor Books Review here.
Want help with your contractor finances?
Schedule a free 20-minute Contractor Books Review.
Book a Contractor Books ReviewContractors only.